Malaysian Environmental Quality Regulations - OLD AND NEW - marceljude.ai
THE OLD
Malaysian environmental subsidiary legislation under the Environmental Quality Act 1974 (Act 127), including: lead concentration in motor gasoline, motor vehicle noise, and prescribed activities requiring environmental impact assessment
The main regulations are the Environmental Quality (Control of Lead Concentration in Motor Gasoline) Regulations 1985, the Environmental Quality (Motor Vehicle Noise) Regulations 1987, and the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987. These instruments all operate under the wider Environmental Quality Act framework, which is Malaysia’s main federal environmental control law. The Act is stated to apply to the whole of Malaysia, although some EIA matters have special treatment for Sabah and Sarawak because of their own state environmental systems. The uploaded compilation is useful for understanding the original 1980s legal structure, but it must be read carefully because part of the EIA regime has since been replaced, and penalties under the Environmental Quality Act have been significantly strengthened by later amendments.
The first regulation, the Environmental Quality (Control of Lead Concentration in Motor Gasoline) Regulations 1985, is aimed at controlling lead pollution from petrol. Its legal approach is direct: it limits the amount of lead or lead compounds, expressed as lead, that may be present in motor gasoline. Under the uploaded regulation, a person could not import or manufacture motor gasoline containing lead above 0.40 gramme per litre after the regulation was gazetted. From 1 January 1986, the same 0.40 gramme per litre limit applied not only to import and manufacture, but also to possession, sale, offering or exhibiting for sale, delivery for use, and exchange for use. Then, from 1 January 1990, the legal limit became stricter: no person could import, manufacture, possess, sell, deliver, or exchange for use motor gasoline containing lead above 0.15 gramme per litre. The regulation also required sampling and analysis to follow the specified procedure, using Malaysian Standards MS 118 and MS 912 or ASTM D 3341, and it required an authorised officer to produce identification before collecting samples and to issue a receipt for the quantity of gasoline collected.
The practical meaning is that the lead regulation creates obligations across the entire fuel chain. It does not only control refineries or importers. A retailer, storage operator, distributor, or party holding gasoline for use may also be exposed if the gasoline exceeds the permitted lead concentration. That is important because environmental product-control regulations usually work by controlling both the upstream supply and the downstream availability of the product. A company handling petrol should therefore not treat the rule as only a manufacturing issue. It should keep batch records, import records, certificates of analysis, laboratory reports, sample receipts, storage records, delivery records, and any export records.
There is also an export exception. Under the uploaded regulation, the restrictions do not apply where motor gasoline is manufactured for export outside Malaysia, but only if prior notice is given to the Director General. That notice must include details such as date of manufacture, quantity, place of storage, customer names, and anticipated export date. The Director General may also establish a recording procedure, and where such procedure is approved, the normal prior-notice requirement may be waived. This means the export exception is not a free exemption. It is a controlled exception based on traceability. If a company claims the gasoline is for export, it should be able to prove that the product was actually manufactured, stored, recorded, and exported as declared.
The regulation also allows a licence to contravene the lead limits in narrow circumstances. A licence may be granted where higher-lead gasoline is needed for investigation or research relevant to pollution problems, for certain rally or racing vehicles, or for a specific use that the Director General considers consistent with the purpose of the regulations. Even then, the Director General must be satisfied that the use is confined to a small segment of the environment and for such a limited period that the accumulated level of lead is unlikely to cause adverse environmental effects. The uploaded regulation shows application fees of RM300 for research or specific-use applications and RM500 for rally or racing purposes.
For modern compliance, the older 0.15 gramme per litre limit should not be treated as the only standard. Later fuel-quality regulations introduced stricter petrol standards. The Environmental Quality (Control of Petrol and Diesel Properties) (Amendment) Regulations 2021 substituted the Malaysian Petrol Standards and set a Euro 5 petrol maximum lead level of 0.005 g/l, with test methods ASTM D3237/D5059, commencing 1 September 2025. This means a current compliance system should apply the strictest relevant legal requirement. In practice, a petrol supplier should screen petrol against the newer Euro 5 petrol standard where it applies, not merely against the older 1985 lead limits.
A sample fuel sampling receipt could read as follows:
SAMPLE FUEL SAMPLING RECEIPT
Receipt Number: DOE-FUEL-2026-014
Date and Time of Sampling: 12 March 2026, 10:30 a.m.
Facility Name: Example Petrol Terminal Sdn Bhd
Product Sampled: RON95 Petrol
Tank / Batch Number: T-95-2026-001
Quantity Collected: Three sample bottles of one litre each
Sample Bottle Numbers: B001, B002, B003
Seal Numbers: SEAL-88421, SEAL-88422, SEAL-88423
The authorised officer produced identification before collecting the sample. The sample was collected for determination of lead concentration in motor gasoline. This receipt is issued for the quantity of sample collected.
Facility Representative:
Name:
Designation:
Signature:
Authorised Officer:
Name:
Designation:
Signature:
The second regulation, the Environmental Quality (Motor Vehicle Noise) Regulations 1987, controls noise emitted by motor vehicles. The regulation defines sound using the dB(A) scale, meaning the sound level is measured with A-weighting, which approximates how the human ear responds to different frequencies. It applies to motor vehicles, including trailers, but the uploaded text excludes vehicles assembled or manufactured before 1 January 1970 and vehicles used for racing purposes in designated racing circuits or approved racing events.
The regulation divides vehicles into two main groups. The first group is vehicles with two or three wheels, such as motorcycles. For these vehicles, the uploaded regulation uses Standard A and Standard B. Standard A applies generally under the original structure: motorcycles of 125 cc and below have a maximum permitted sound level of 95 dB(A), while those above 125 cc have a maximum permitted level of 99 dB(A). Standard B applies to two-wheel or three-wheel vehicles manufactured or assembled on or after 1 January 1990: vehicles below 90 cc have a maximum of 92 dB(A), and vehicles of 90 cc and above have a maximum of 95 dB(A).
The second group is vehicles with more than three wheels. The uploaded regulation sets Standard C limits. Passenger vehicles with not more than nine seats, including the driver’s seat, are limited to 80 dB(A). Passenger vehicles with more than nine seats and a permitted maximum weight not exceeding 3.5 tonnes are limited to 81 dB(A). Goods vehicles not exceeding 3.5 tonnes with engines below 200 hp DIN are also limited to 81 dB(A). Heavier passenger vehicles and goods vehicles have higher limits depending on weight and engine power, with the highest listed limit being 88 dB(A) for goods vehicles exceeding 3.5 tonnes with engines of 200 hp DIN or more.
The testing procedure is as important as the limit itself. For two-wheel and three-wheel vehicles, the sound level meter must meet Type 1 or Type 0 requirements under IEC Publication 651, measurements must use A-frequency weighting and F-time weighting, and calibration must be checked at the beginning and end of each measurement series. If the calibration error changes by more than 1 dB, the test is invalid. The test site must be a flat hard reflective surface such as concrete or asphalt, not earth. The background noise must be at least 10 dB below the measured test noise, and measurements must not be made in adverse weather or where wind speed at microphone height exceeds 5 m/s. At least three measurements must be made at each measuring position, and the measurements are valid only if the range of the three immediate measurements is not greater than 2 dB. The final result is the arithmetic mean.
For motorcycles and similar vehicles, microphone placement is also controlled. The microphone must be at the height of the exhaust outlet, but not less than 0.2 metre above the ground, and it must be placed 0.5 metre from the exhaust outlet. The engine must be brought to normal operating temperature. Engine speed must be stabilised at half the maximum-power engine speed if that maximum-power speed is greater than 5000 rpm, or at three-quarters of the maximum-power engine speed if it is less than 5000 rpm. The throttle is then closed suddenly, and the highest noise level during the brief constant-speed and deceleration period is recorded.
For vehicles with more than three wheels, the testing process is different. The sound level meter must at least meet Type 1 requirements under IEC Publication 651, and the instruments used to measure engine speed and road speed must have accuracy of 3% or better. The test site must be substantially level, dry, and free from large reflecting objects within a radius of 50 metres around the centre of the track. The microphone is placed 7.5 metres from the reference line of the track and 1.2 metres above ground level. At least two measurements must be made on each side of the vehicle, and the results are valid only if two consecutive measurements on the louder side do not differ by more than 2 dB. For this category, the highest valid value becomes the result.
A sample motorcycle noise test conclusion could read:
SAMPLE MOTORCYCLE NOISE TEST CONCLUSION
Vehicle: Motorcycle
Engine Capacity: 110 cc
Year of Manufacture: 2023
Applicable Category: Two-wheel vehicle, 90 cc and above, manufactured after 1 January 1990
Applicable Limit: 95 dB(A)
Measurements Taken:
First measurement: 94.1 dB(A)
Second measurement: 94.6 dB(A)
Third measurement: 94.4 dB(A)
Validity Check:
The range between the lowest and highest readings is 0.5 dB. This is within the permitted 2 dB range, so the measurements are valid.
Final Result:
The arithmetic mean is 94.4 dB(A).
Decision:
PASS. The measured sound level does not exceed the 95 dB(A) limit.
A sample failed motorcycle test could read:
SAMPLE FAILED MOTORCYCLE NOISE TEST CONCLUSION
Vehicle: Motorcycle
Engine Capacity: 70 cc
Year of Manufacture: 2023
Applicable Category: Two-wheel vehicle below 90 cc, manufactured after 1 January 1990
Applicable Limit: 92 dB(A)
Measurements Taken:
First measurement: 92.7 dB(A)
Second measurement: 93.1 dB(A)
Third measurement: 93.0 dB(A)
Validity Check:
The range is 0.4 dB, so the test series is valid.
Final Result:
The arithmetic mean is 92.9 dB(A).
Decision:
FAIL. The measured sound level exceeds the 92 dB(A) limit.
A sample completed motor vehicle noise record could read:
SAMPLE RECORD OF TESTS
Registration Number: WXX 1234
Test Number: MVN-2026-001
Measurement Procedure
:
Third Schedule procedure for motor vehicles having two wheels or three wheels.
Category of Vehicle:
Motorcycle, 90 cc and above, manufactured after 1 January 1990.
Vehicle Details:
Make: ExampleMoto
Model: EM110
Engine Capacity: 110 cc
Horsepower: 8 hp
Transmission: Manual
Fuel: Petrol
Exhaust System: Factory standard exhaust
Test Site:
Hard asphalt surface.
Weather Conditions:
Wind speed: 2.0 m/s
Rain: None
Measurement Instruments:
Sound Level Meter: Type 1 sound level meter
Engine Tachometer: Calibrated tachometer
Windscreen: Used
Engine Operating Speed:
3,750 rpm
Background Sound Level:
64 dB(A)
Number of Measurements:
Three
Sound Level of Vehicle Tested:
94.4 dB(A)
Applicable Legal Limit:
95 dB(A)
Conclusion:
The vehicle passes the sound level test.
Authorised Officer:
Name:
Signature
:
For Director General of Environmental Quality
The third instrument in the uploaded material is the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987. This order was made under section 34A of the Environmental Quality Act and listed activities that required environmental impact assessment. The uploaded 1987 Order covered many project categories, including agriculture, airports, drainage and irrigation, land reclamation, fisheries, forestry, housing, industry, infrastructure, ports, mining, petroleum, power generation and transmission, quarries, railways, transportation, resort and recreational development, waste treatment and disposal, and water supply. Examples from the uploaded order include housing development of 50 hectares or more, coastal reclamation of 50 hectares or more, irrigation schemes of 5,000 hectares or more, land-based aquaculture involving mangrove clearing of 50 hectares or more, logging of 500 hectares or more, construction of ports, construction of expressways, oil and gas field development, pipelines over 50 kilometres, fossil-fuel steam power stations above 10 megawatts, and groundwater development above 4,500 cubic metres per day.
However, the 1987 EIA Order is not the current main order for new projects. The current federal EIA screening instrument is the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015. The 2015 Order states that activities specified in its First Schedule and Second Schedule are prescribed activities, and it expressly revokes the 1987 Order, subject to saving and transitional provisions for reports already approved or received before the new order came into operation. This is the most important legal update in the whole research brief. The uploaded 1987 EIA list is useful historically, but anyone screening a current project must use the 2015 Order, not rely only on the 1987 schedule.
The 2015 Order creates a clearer distinction between First Schedule and Second Schedule activities. First Schedule activities are prescribed activities but do not require public display and public comment unless the Director General instructs otherwise in writing. Second Schedule activities require public display and public comment. The Order also contains an anti-avoidance rule: a project remains a prescribed activity if it is divided into smaller sizes or quantities to fall below the listed threshold, and an activity also becomes prescribed if an increase in size or quantity brings it within a prescribed category. This means a developer cannot safely avoid EIA by artificially splitting one project into several smaller project packages.
Section 34A of the Environmental Quality Act is the legal foundation for the EIA process. In practical terms, if a proposed activity is a prescribed activity, the project proponent must prepare and submit an EIA report to the Director General before approval is granted by the relevant approving authority and before the activity is carried out. The purpose of the report is to assess likely environmental impacts and to propose measures to prevent, reduce, or control adverse impacts. Once conditions are attached to an approved EIA, they must be built into the project’s design, construction, operation, monitoring, and reporting.
A sample EIA screening conclusion for a housing project could read:
SAMPLE EIA SCREENING CONCLUSION — HOUSING DEVELOPMENT
Project:
Proposed residential development on 60 hectares of land.
Legal Screening:
The project is screened under the Environmental Quality Act 1974 and the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015.
Finding:
Housing development covering 50 hectares or more is a prescribed activity. Because the proposed project covers 60 hectares, it falls within the EIA requirement.
Public Display:
The project appears to fall under the First Schedule. Public display and public comment are not automatic unless the Director General instructs otherwise in writing.
Conclusion:
The project proponent should prepare and submit an EIA report before seeking final project approval and before carrying out project works.
A sample EIA screening conclusion for a petrol or diesel depot could read:
SAMPLE EIA SCREENING CONCLUSION — PETROL AND DIESEL DEPOT
Project:
Proposed petrol and diesel product depot.
Storage Capacity:
70,000 barrels.
Location:
Approximately 2 kilometres from a residential area.
Legal Screening:
A product depot for petrol, gas, or diesel, excluding service stations, may become a prescribed activity where it has a combined storage capacity of 60,000 barrels or more and is located within 3 kilometres of a commercial, industrial, or residential area.
Finding:
The proposed depot exceeds 60,000 barrels and is within 3 kilometres of a residential area.
Conclusion:
The project is likely to be a prescribed activity and should proceed through the EIA
A sample EIA screening conclusion for aquaculture could read:
SAMPLE EIA SCREENING CONCLUSION — AQUACULTURE PROJECT
Project:
Land-based aquaculture project involving clearing of mangrove forest.
Clearing Area:
40 hectares.
Legal Screening:
Under the 2015 EIA Order, land-based aquaculture accompanied by clearing of mangrove forest, peat swamp forest, or freshwater swamp forest may be prescribed depending on the area cleared.
Finding:
A 40-hectare clearing falls within the lower prescribed range and would generally be treated as a First Schedule activity.
Conclusion:
An EIA report should be prepared. Public display and public comment would not normally be automatic unless instructed by the Director General.
Additional Note:
If the clearing were 50 hectares or more, the project would likely move into the more serious Second Schedule pathway, requiring public display and public comment.
A sample EIA screening memorandum could read:
SAMPLE EIA SCREENING MEMORANDUM
Project Name:
Proposed 60-Hectare Housing Development at [Insert Location]
Project Proponent:
ABC Development Sdn Bhd
Purpose of Memorandum:
This memorandum screens the proposed development to determine whether it is a prescribed activity requiring environmental impact assessment.
Project Description:
The project involves residential development over approximately 60 hectares, including land clearing, earthworks, internal roads, drainage, utilities, and housing units.
Legal Framework:
The relevant legal framework is the Environmental Quality Act 1974, especially section 34A, and the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015.
Screening Finding:
Housing development covering 50 hectares or more is a prescribed activity. The proposed project covers 60 hectares and therefore falls within the prescribed activity threshold.
Public Display and Public Comment:
The project appears to fall within the First Schedule. Public display and public comment are not automatically required unless the Director General instructs otherwise in writing.
Key Environmental Issues:
The EIA should assess land clearing, erosion and sediment control, drainage and flood risk, traffic, construction noise, air quality, water quality, waste management, effects on nearby communities, and long-term environmental monitoring.
Anti-Avoidance Note:
The project should not be divided into smaller phases or packages for the purpose of avoiding the EIA threshold. If the project is phased, the full development concept should still be considered in screening.
Recommendation:
The proponent should appoint a competent environmental consultant, consult DOE at an early stage, prepare the EIA report, and ensure that no prescribed works are carried out until the required approval is obtained.
The penalty position is also important. The older uploaded material must be read together with later amendments to the Act. The Environmental Quality (Amendment) Act 2024 strengthened penalties across the Act. For noise pollution under section 23, the amended penalty is a fine of not less than RM10,000 and not exceeding RM250,000, imprisonment up to five years, or both, with a further daily fine after notice. For section 34A EIA breaches, the amended penalty is imprisonment up to five years and a fine of not less than RM100,000 and not exceeding RM1,000,000. This means the legal risk is no longer merely administrative. A serious breach can involve prosecution, high fines, imprisonment exposure, stop-work consequences, reputational damage, project delay, and difficulty obtaining future approvals.
Overall, the lead concentration regulation is best understood as a fuel-quality and pollution-prevention control. Its compliance focus is laboratory proof, sampling integrity, recordkeeping, and strict control of exceptions. The motor vehicle noise regulation is best understood as a technical measurement regime. Its compliance focus is correct classification of the vehicle, correct decibel limit, proper test-site conditions, calibrated instruments, valid measurement ranges, and proper recording. The EIA order is best understood as a project-screening and approval-control regime. Its compliance focus is early identification of prescribed activities, submission of an EIA report before approval and implementation, public participation where required, and full implementation of mitigation conditions.
A strong compliance system should therefore keep one legal register covering all three areas. For petrol, it should record product type, batch number, tank number, date, applicable lead limit, laboratory method, result, certificate of analysis, sampling officer, sample seal, and corrective action. For vehicle noise, it should record vehicle type, engine size, date of manufacture, applicable standard, sound level meter details, calibration records, background sound, wind speed, raw readings, final result, and authorised officer details. For EIA, it should record project description, location, land area, capacity, distance from sensitive receptors, relevant prescribed activity category, First Schedule or Second Schedule classification, DOE correspondence, EIA approval conditions, monitoring duties, and evidence that mitigation measures were built into design and construction.
The most important practical conclusion is that the uploaded regulations cannot be used in isolation. They show the original legal structure, but a proper modern compliance answer must include current updates. The old lead limits must be read alongside newer petrol-quality standards, especially the Euro 5 petrol lead maximum of 0.005 g/l from 1 September 2025. The 1987 EIA Order must be treated as historical for new projects because the 2015 EIA Order revoked and replaced it. The motor vehicle noise regulation remains important as a technical standard, but enforcement risk must be assessed using the current penalty provisions under the amended Environmental Quality Act.
THE NEW RULES
Current position: the “new rules” and how they replace or update the older regulations
The above is the older 2008 compilation of Malaysian environmental subsidiary legislation. It contains the older Environmental Quality (Control of Lead Concentration in Motor Gasoline) Regulations 1985, the Environmental Quality (Motor Vehicle Noise) Regulations 1987, and the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987. In that older framework, petrol lead control was handled mainly by direct lead concentration limits of 0.40 g/l and later 0.15 g/l, motor vehicle noise was controlled by the 1987 noise standards and test procedures, and EIA was controlled by one 1987 schedule of prescribed activities.
The important point now is that the three areas have not all been replaced in the same way. The EIA rules have been formally replaced. The fuel lead rules have been overtaken in practice by newer petrol and diesel property standards, although the older lead regulation still appears on DOE’s list of air-division regulations. The motor vehicle noise rules have not been replaced; DOE still states that motor vehicle noise is controlled under the 1987 Motor Vehicle Noise Regulations. The 2024 amendment to the Environmental Quality Act then sits above all of these and makes the penalty/enforcement environment much stricter. DOE’s current Air Division list still includes the 1985 lead regulation, the 1987 motor vehicle noise regulation, and the 2021 petrol and diesel content/property regulation, which shows that the modern framework is layered rather than a simple deletion of every old regulation.
For petrol lead content, the older uploaded rule was narrow. It focused specifically on lead in motor gasoline and moved from a 0.40 g/l limit to a 0.15 g/l limit. The newer rule is much broader. The current modern control is found in the Environmental Quality (Control of Petrol and Diesel Properties) Regulations 2007, as amended by the Environmental Quality (Control of Petrol and Diesel Properties) (Amendment) Regulations 2021. The 2021 amendment expressly amends the 2007 principal regulations by substituting the First Schedule, and the substituted Malaysian Petrol Standards set Euro 5 petrol lead at a maximum of 0.005 g/l, with ASTM D3237/D5059 as the listed test methods and commencement on 1 September 2025.
This means the newer petrol rule does not merely repeat the old lead rule; it changes the compliance question. Under the old uploaded regulation, a petrol batch with 0.12 g/l lead would have been below the old 0.15 g/l limit. Under the modern Euro 5 petrol standard, the same batch would fail because 0.12 g/l is far above 0.005 g/l. So, for a present-day petrol supplier, importer, refinery, terminal, or retailer, the old question “Is the petrol below 0.15 g/l?” is no longer enough. The current question is “Does the petrol meet the full current petrol property standard, including the Euro 5 lead maximum of 0.005 g/l where applicable?” In that sense, the newer petrol/diesel property regulations functionally replace the old lead-only standard for ordinary petrol compliance, even if the 1985 regulation still remains listed separately.
A sample current compliance conclusion would read like this: “The petrol batch was tested for lead using ASTM D3237/D5059. The result was 0.003 g/l. The applicable Euro 5 petrol maximum is 0.005 g/l. The batch is compliant and may be released, subject to all other petrol property requirements.” A failing example would read: “The petrol batch recorded 0.02 g/l lead. Although this would have been below the older 0.15 g/l lead-control threshold, it exceeds the current Euro 5 petrol maximum of 0.005 g/l. The batch must not be released for ordinary supply unless lawfully dealt with under an approved corrective or disposal route.”
For motor vehicle noise, the position is different. There is no clear replacement of the 1987 Motor Vehicle Noise Regulations. DOE’s own motor vehicle noise page still states that noise emission from motor vehicles is controlled under the Environmental Quality (Motor Vehicle Noise) Regulations 1987, and that motorcycle noise enforcement has been carried out by DOE state offices with the Royal Malaysia Police Traffic Branch.
So, unlike the EIA Order, the motor vehicle noise regulation is not something you should describe as revoked or replaced. The older decibel categories and testing procedures remain the basic technical framework. The “new” legal position is mainly that the enforcement environment around the Environmental Quality Act has become stricter. In practice, this means the old test still matters: the vehicle must still be classified correctly, the correct dB(A) limit must still be applied, the sound level meter must be calibrated, background noise and wind conditions still matter, and the result must still be recorded properly. But the consequences of breaching environmental controls are now heavier because of later amendments to the parent Act.
A sample current motor vehicle noise conclusion would therefore not say, “The 1987 rule has been replaced.” It should say: “The applicable technical regulation remains the Environmental Quality (Motor Vehicle Noise) Regulations 1987. The vehicle was tested under the relevant schedule. The measured result was compared with the applicable dB(A) limit. The vehicle either passes or fails under the 1987 regulation, while enforcement and penalties are assessed under the Environmental Quality Act as amended.”
The biggest formal replacement is in environmental impact assessment. The old uploaded document contains the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987. That old order used one schedule of prescribed activities. It covered broad categories such as agriculture, airports, drainage and irrigation, reclamation, fisheries, forestry, housing, industry, infrastructure, ports, mining, petroleum, power generation, quarries, railways, transportation, resort development, waste treatment and water supply.
For current EIA screening, that 1987 order has been replaced by the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015. The 2015 Order expressly states that the activities in its First Schedule and Second Schedule are prescribed activities. It also says that First Schedule activities do not require public display and public comment unless the Director General instructs otherwise in writing, while Second Schedule activities require public display and public comment. It also adds an anti-avoidance rule: a project is still treated as prescribed if it is split into smaller sizes or quantities to avoid the threshold, or if an increase in size or quantity brings the activity into a prescribed category.
The replacement is express. The 2015 Order says the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987 is revoked. It also contains saving and transitional rules: if an EIA report under the revoked 1987 Order had already been approved before the 2015 Order came into operation, that approval is not affected; if a report had already been received before the 2015 Order came into operation, it is dealt with as if the new order had not been made; but if it is later resubmitted after non-approval, it is dealt with under the 2015 Order.
This means that for a new project today, you should not screen it using the 1987 EIA schedule as the main law. You screen it under the 2015 Order. The old 1987 Order is mainly useful for historical projects, old approvals, transitional reports, and comparison.
The 2015 Order also changes the structure of EIA. Under the old 1987 Order, the schedule was basically one list. Under the new 2015 Order, the question is more refined: first, is the activity prescribed at all; second, does it fall under the First Schedule or the Second Schedule; third, is public display and public comment required; fourth, does the project involve environmentally sensitive areas; and fifth, is there any attempt to split the project to avoid the threshold? This is a much stronger screening system than the old one.
For example, under the old uploaded 1987 Order, an agricultural land development scheme involving forest land generally became prescribed at 500 hectares or more. Under the 2015 Order, there is now a First Schedule trigger for land development schemes covering 20 hectares or more but less than 500 hectares to bring forest into agricultural production, while 500 hectares or more appears in the Second Schedule. This changes the legal result. A 100-hectare forest-to-agriculture project might not have been caught by the older 500-hectare trigger, but under the 2015 Order it can now fall into the First Schedule and require an EIA process, although public display is not automatic unless directed by the Director General.
Another example is an industrial estate. The uploaded 1987 Order referred to industrial estate development for medium and heavy industries covering 50 hectares or more. Under the 2015 Order, development of an industrial estate covering 20 hectares or more appears in the First Schedule. This lowers the practical threshold and expands DOE oversight. A 30-hectare industrial estate that might previously have sat below the old 50-hectare threshold may now be a prescribed activity.
A third example is aerodrome development. The old uploaded 1987 Order referred to construction of airports with an airstrip of 2,500 metres or longer. Under the 2015 Order, expansion of an aerodrome involving a runway of 1,000 metres or longer appears in the First Schedule, while construction of a new aerodrome involving a runway of 1,000 metres or longer appears in the Second Schedule. The Second Schedule also covers construction of an aerodrome in, adjacent to, or near certain parks, marine parks, islands surrounding marine parks, or environmentally sensitive areas. So a new 1,200-metre runway project is now a more serious EIA matter than it would have appeared under the old 2,500-metre airport threshold.
The newer EIA rules also deal more clearly with sensitive ecosystems. For land-based aquaculture, the First Schedule covers clearing of mangrove forest, peat swamp forest, or freshwater swamp forest of 20 hectares or more but less than 50 hectares, while the Second Schedule covers 50 hectares or more. A 40-hectare aquaculture clearing project would therefore be a First Schedule EIA matter. A 60-hectare project would move into the Second Schedule and require public display and public comment.
The 2015 Order also introduces and uses the idea of an environmentally sensitive area. It defines this by reference to areas specified in development plans or the National Physical Plan under the Town and Country Planning Act 1976, or areas specified as environmental protection or conservation areas under Sabah or Sarawak law. This matters because some activities become more tightly controlled when they are in, adjacent to, or near sensitive areas. Under the older 1987 system, the schedule was less developed in that way.
For EIA procedure, DOE’s current public guidance confirms that an EIA is required where the proposed project is stipulated under the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015. DOE also states that Sabah and Sarawak have their own state-level EIA legislation for certain activities, and that EIA and EMP reports must be prepared by EIA consultants registered with DOE through the myCEP system. This is another practical change from simply reading the old 1987 schedule: current EIA compliance now requires checking the 2015 federal order, checking Sabah/Sarawak state requirements where relevant, and using the correct consultant route.
A sample current EIA screening statement would read: “The proposed project is a 30-hectare industrial estate. Under the 1987 Order, the earlier threshold focused on medium and heavy industrial estates of 50 hectares or more. Under the 2015 Order, development of an industrial estate covering 20 hectares or more is a First Schedule prescribed activity. The project therefore requires EIA submission under the current 2015 Order. Public display and public comment are not automatic unless the Director General instructs otherwise in writing.”
Another sample would read: “The proposed project is a new aerodrome with a 1,200-metre runway. Under the current 2015 Order, construction of a new aerodrome involving a runway of 1,000 metres or longer is a Second Schedule activity. The project therefore requires EIA and public display/public comment. The old 1987 airport threshold should not be used for a new current project.”
The final major update is the Environmental Quality (Amendment) Act 2024, Act A1712. This does not replace the three subsidiary instruments one by one, but it changes the parent Act under which they operate. For EIA, the amendment replaces the section 34A penalty so that a person who contravenes section 34A commits an offence punishable by imprisonment up to five years and a fine of not less than RM100,000 and not more than RM1,000,000. The same amendment also changes section 51 so that regulations made under the Act may prescribe offences with penalties up to RM100,000, imprisonment up to five years, or both, and for continuing offences a further amount up to RM1,000 for each day the offence continues.
This means the current legal environment is stricter than the uploaded 2008 material suggests. Under the old way of thinking, some parties treated EIA, petrol quality, or vehicle-noise compliance as technical paperwork. Under the modern system, these are enforcement-risk issues. For EIA especially, starting a prescribed activity without the required approved EIA can now expose the project proponent to much heavier consequences. For petrol and diesel, the technical product specification is stricter. For vehicle noise, the technical rule remains the 1987 regulation, but enforcement sits inside a stronger amended Act.
In short, the replacement position is this: the 1987 EIA Order is formally replaced by the 2015 EIA Order; the 1985 lead regulation is not simply the main modern petrol standard anymore because the 2007 petrol/diesel properties regime, especially the 2021 Euro 5 amendment, now sets much stricter petrol specifications; and the 1987 Motor Vehicle Noise Regulations remain the current technical noise-control regulations rather than being replaced. The 2024 amendment to the Environmental Quality Act then strengthens penalties and enforcement across the environmental regime.